MedImmune

  • Project Photo
  • Project Photo
  • Project Photo
Location
Frederick, MD
Project Value
$500 mlnTIV/$52,000,000 Kinetics
Date of start
September 2007
Date of completion
April 2009
Contract with
Fluor
Engineer
Parsons
Architect
Parsons

The scope of work for this project included:

  • Installation of all FDA validated and non-validated orbital welded stainless steel piping systems including WFI, Pure Steam, CIP and product piping with strict QA/QC requirements and 100% boroscope inspection
  • Installation of all schedule 10 stainless steel water, drain and vent piping systems
  • Installation of in-suite gas piping
  • Rigging and installation of process equipment including pumps, heat exchangers and skids;
  • Process vessel trim;
  • Subcontracts for piping insulation, rigging and passivation.

Click here to download project profile.